Current Project Activities
The current project at the former TBR has two objectives: performance of a Remedial Investigation and Feasibility Study (RI/FS) and preparation and stakeholder approval of a Decision Document for the site. The tasks associated with these objectives involve both field-related procedures (e.g., site visits, physical investigations, and data analysis) and community-related elements (e.g., USACE solicitation and consideration of community input from interviews, surveys, and other sources; public presentations; community review of project documents; and implementation of a public involvement program).
This page provides a chronological overview of some of the primary project tasks (based on presumed start-dates; tentative dates are listed in parentheses). Where appropriate, the entry includes links to related documents, visuals, sources of additional information, public involvement opportunities, and other items of interest.
2005
|
27 June and 18 August:
|
Technical Project Planning (TPP) Meetings held in Rancho Santa Margarita.
(The TPP process is designed to define and articulate the desired site closeout
condition, and create a plan with the actions necessary to reach this goal,
all with stakeholder acceptance.
Initial meetings bring a number of stakeholders
together for an introduction to the site and project objectives and to begin
the formal planning process.)
In conjunction with the first meeting, project
team members conduct a site visit to develop familiarity with the current
configuration of the project area.
|
|
1 July to 31 October:
|
Project team members conduct community background interviews
for the PIP. Web-enabled survey opened to give local residents an
opportunity to provide input as background for the Public Involvement
Plan (PIP). |
|
27 October:
|
Third TPP meeting and a Public Availability Session/Open House conducted in Rancho Santa Margarita.
Draft Public Involvement Plan (PIP) released for public review and comment.
|
2006
|
January:
|
Final Public Involvement Plan issued.
|
|
January:
|
Geophysical Prove-Out field activities conducted at the project site.
|
|
20 July:
|
Fourth and final TPP meeting held in Rancho Santa Margarita.
|
|
5 October:
|
Final Work Plan for field activities distributed. |
|
16 October:
|
Geophysical investigation activities began in selected areas of the
Site.
|
|
30 November:
|
Consolidated demolition of six suspected munitions and explosives of concern found during the field investigation. |
|
6 December:
|
Field activities completed. Project personnel began compiling data collected in the field and assembling the RI/FS report.
|
2007
|
|
Review of field data; preparation of RI/FS documentation. |
2008
|
Spring:
|
The Draft RI/FS report is scheduled for distribution to stakeholders for review, and it will be posted on this Web site. |
|
If you find suspicious items that may be military ordnance/munitions, DO NOT TOUCH! Mark the area for identification and call 911 immediately!
|
©copyright 2005-2008, Innovative Technical Solutions, Inc.